Table of Contents and Snapshot
Summary (PDF)
Chapter 2 - Construction,
Commissioning & Production (PDF)
Significant advances this quarter have put the Project within reach of its
goal to commence crude oil production in mid-2003.
Crews on the Project's five oil well rigs had drilled a total of 60 production
wells by the end of the quarter and drilling operations are now underway in
all three oilfields in southern Chad.
Work on the crude oil export system was moving ahead on schedule.
- Construction was nearly finished on Pump Stations 1 and 2, the two pipeline
system pump stations required for initial oil production.
- At the terminus of the onshore pipeline, near Kribi, Cameroon, the Pressure
Reducing Station had been 100% completed.
- The pipeline itself was completely welded, lowered into its trench, and
buried. Finishing touches were underway, including final integrity testing of
the pipeline and reclamation of the right of way.
Significant progress was made during the quarter on the oilfield area
facilities.
- The Central Treatment Facility that will process crude oil before it is put
into the pipeline was more than 98% complete for the purpose of the initial
start up.
- Electrical generation and distribution systems were almost finished and
testing had started.
The components of the marine terminal were beginning to come together as the
quarter ended.
- The Floating Storage and Offloading vessel was about to start sea trials in
Singapore and the Single Point Mooring unit had already been barged 90% of the
distance from Malaysia to Cameroon.
- Trenching was underway for the installation of the 12 kilometer undersea
pipeline that will connect the onshore pipeline to the Floating Storage and
Offloading vessel.
Chapter 3 - Reportable EMP
Situations (PDF)
This quarter's total of 16 Environmental Management Plan non-compliance
situations was the lowest number recorded since Project construction began in
October 2000. However, for the first time, Level III non-compliance situations
were recorded.
- The Level III situations, which were asserted and recorded by the World Bank
Group, involved the Project's management of three archaeological sites along
the pipeline route in Cameroon.
- The Project has developed a go-forward program that is consistent with
previous plans, expands the availability of the Project's archaeological
findings, and adds capacity-building elements to the Project's comprehensive
archaeology program.
Note: For full details concerning this matter please see the section on
Reportable EMP Situations, as well as the section on
Archaeology & Cultural Resources (chapter 10).
Chapter 4 - Safety
(PDF)
The overall worker safety record at Project work sites continued to be very
good.
- The Recordable Incident Rate held steady at 0.5 incidents per 200,000 work
hours.
- Workers for facilities construction contractor TCC have topped the 29
million hour mark without a lost time incident.
- One Project-recordable lost time incident occurred this quarter at the
shipyard in Singapore where renovation of the Floating Storage and Offloading
vessel was taking place.
Chapter 5 - Consultation &
Communication (PDF)
The Project conducted over 370 public consultation sessions in the first
quarter of 2003, reaching over 18,000 people.
- Consultation sessions focusing on the Project's Area Specific Oil Spill
Response Plans were held in numerous communities in Chad and Cameroon.
- Two consultation teams began working their way along the pipeline route to
prepare the local population for the impending start of production, when crude
oil will begin flowing in the pipeline.
Chapter 6 - Compensation
(PDF)
Since the Project's compensation program began, approximately 7.2 billion FCFA
($11 million) in cash and in-kind payments has been distributed to individual
land users.
- In Chad, individual compensation distributed in the first quarter totaled
over 202 million FCFA ($311 thousand).
- In Cameroon, individual compensation paid in the first quarter was nearly
192 million FCFA ($295 thousand).
Work continued on the Project's regional and community compensation programs.
- In Cameroon, 150 of the villages eligible for the programs had received
deliveries of various improvements they had chosen. Materials delivered
include school equipment and supplies, medical equipment and medicines,
community brick making equipment, and water wells with hand or foot pumps.
- In Chad, 77 of the 86 eligible communities have chosen their compensation.
The chosen improvements include multi-room schools, wells with pumps, and
market places.
Chapter 7 - EMP Monitoring &
Management Program (PDF)
A rigorous environmental monitoring program was launched this quarter in the
vicinity of the Project's shoreline worksite near Kribi, Cameroon. A
particular focus of the effort is the protection of sea turtles that sometimes
are found in the area. So far, daily pre-work inspections have not found any
turtles.
The Project enhanced its dust control program in Chad this quarter. Tests of
several dust suppression options showed that a road coating of industrial
molasses was very effective. Treatment of the Project's main oilfield area
road was underway at the quarter's end.
The Project's ambient air quality monitoring program was launched with the
installation of two monitoring stations and the training of Chadian and
Cameroonian technicians to operate and maintain them.
Another fire at Komé Atan destroyed a section of the village that was left
largely untouched by last quarter's fire. The cause of the fire is unclear.
Rebuilding had already started by the end of the quarter.
Chapter 8 - Local Employment
(PDF)
Construction worker demobilization is now well underway in both Chad and
Cameroon, and the size of the Project's direct workforce has declined to just
over 10,000 workers, down from the peak total of over 13,000 in November 2002.
- Well over 7,000 Chadian and Cameroonian workers remained on the job at the
quarter's end, well above the originally projected peak local employment level
of 4,000.
- Since construction began, it is estimated that more than 35,000 workers have
held jobs with the Project.
Wages paid to Chadian and Cameroonian workers in the first quarter of 2003
totaled more than 6.6 billion FCFA ($10.1 million).
- Wage payments to Chadian workers exceeded 3.9 billion FCFA ($6.0 million).
- Wage payments to Cameroonian workers exceeded 2.7 billion FCFA ($4.1
million).
Chapter 9 - Local Business
Development (PDF)
The Project spent over 52.5 billion FCFA ($81 million) procuring goods and
services from Chadian and Cameroonian suppliers during the first quarter.
Since construction began, the Project has made local purchases of over 398
billion FCFA ($612 million).
Chapter 11 - Worker Health
(PDF)
Project clinics provided over 18,000 worker medical consultations during the
first quarter of 2003.
- The number of malaria cases among non-immune workers dropped significantly
this quarter compared to the same quarter in 2002, even though the size of the
non-immune work force more than doubled in the same period.
- The Project's malaria-related hospitalization rate for semi-immune workers
continues to run at a level that is approximately one-ninth the rate of the
overall population in Chad and Cameroon.
Chapter 12 - Community Health
(PDF)
One of the final procedural steps was taken toward establishing a new public
health diagnostic and research center to be based in the oilfield area. The
Southern Chad Reference Center for Infectious Diseases will provide diagnostic
and educational support for the five clinics operating in the oilfield area.
(It should be noted that the facility will not provide direct patient care.)
Chapter 13 - Waste Management
(PDF)
Work was nearly completed on the engineered solid waste landfill at the Komé
Waste Management Facility in the oilfield area. Liner installation was
finished and only the installation of some pumps and other infrastructure
remains before the facility can become operational.
Chapter 14 - Environmental
Foundation (PDF)
The Management Board for the Foundation for Environment and Development in
Cameroon has formally launched its ecological, conservation, and enhancement
programs in two new national parks.
- The Board signed a funding agreement with the Wildlife Conservation Society
for the program in the Campo-Ma'an national park.
- The Board signed a similar agreement with the World Wildlife Fund to conduct
the program in the Mbam and Djerem national park.
Chapter 15 - Transition to
Oil Production Phase (PDF)
With construction progress on schedule for initial oil production to commence
at mid-year, several significant steps have been taken in the building of the
Project's operations phase organization.
- Training was completed for most of the expatriate staff that will hold
operations jobs in Chad and Cameroon. Over 70 expatriates had begun their work
assignments in the two host countries.
- A new wave of recruiting for additional permanent Chadian and Cameroonian
operations organization staff was about to begin. A total of 177 Chadians and
Cameroonians are currently employed as permanent staff.
- As the quarter closed, the operations organization was about to take control
of its first facility, the Pressure Reducing Station near Kribi, Cameroon.
- The first of a number of major contracts that will support operations
activities has been signed, a contract for logistics services.
Download Full Report (PDF)
|